Rubey Park Bathroom Stalls revised 4_9_2013.pdf
- Library: Purchissues
- Year Created: 2013
- File Type: PDF
The document is an informal procurement memorandum regarding a small project for the replacement of men's and women's bathroom stall dividers at Ruby Park. The timeline for the project is set for May 14-19, 2013, with a budget of $20,000. Two contractors were contacted, BOY-KO Supply and Aspen Maintenance Supply, with proposals received from both. Aspen Maintenance Supply was chosen due to better pricing and their willingness to store the materials until installation day. The selected contractor provided a detailed breakdown of the required items for installation, including stainless steel doors, pilasters, grab bars, and custom components. The total cost for the project with Aspen Maintenance Supply was $9690.98, with an estimated freight cost of $948.00. The document also mentions the requirement for a certificate of insurance if the contractor will be working on RFTA property.