NSITE DOCUMENT
Substantial Completion Letter.doc
- Library: Purchissues
- Year Created: 2017
- File Type: DOC
The document is a notice of substantial completion for the Riverside Business Park Natural Gas Improvements – Trail Extension and Buffer Enhancements project. It informs Kyle Smith that the substantial completion date was December 5, 2014, and includes a Substantial Completion Certificate for signature. The warranty periods start from the substantial completion date. Final completion, triggered by meeting all contractual requirements, must be achieved within 15 days of substantial completion. The document lists the requirements for final completion, such as completing punchlist items, submitting final invoices, providing records of payments to subcontractors, and obtaining necessary approvals.