NSITE DOCUMENT
16-167 Tentative Project Timeline dt 12-3-15.xlsx
- Library: Purchissues
- Year Created: 2016
- File Type: XLSX
The document outlines a project timeline for an Internet Service Provider starting from the advertisement for a Request for Proposal (RFP) on March 11, 2016, to the project going live on June 1, 2016. It includes key milestones such as the RFP being issued to the public on March 17, questions from vendors due by March 31, evaluation of the RFP by the Evaluation Team from April 18 to April 29, SCC Board Approval on May 16, and the project beginning on May 20 after the contract is signed.