The document outlines the guidelines and procedures for a Design/Build project at the University of Maryland College Park. It specifies that only the Design/Build Contractor (DBC) or its subsidiaries/affiliates can bid for work on the project if approved by the University. The DBC must request approval in writing at least 60 days before the bid due date, detailing the proposed work package, bidding company information, and project benefits. The University has access to all project meetings and DBC records, paying fixed fees for construction and general conditions. Design/Build procedures should integrate all project components efficiently and meet quality standards. The DBC is expected to lead the Contractor's Design Team in the University's best interests.